Xavier College Theatre
Scaffolding the new 450 seat theatre at this Melbourne college required a 350m² suspended mat scaffold that appears to float above the auditorium. Supported only at each end it spans over 18m from front to back, and from side to side it spans up to 20m without additional support.
Month ahead of schedule
Walton Construction’s Site Manager Neil Timms said, “Not only did the fast installation of Layher Allround enable us to start the project one month ahead of schedule, it also gave us the ability to overlap trades on site to save time; something that could not be achieved using other systems.” Neil also mentioned that “by doing away with the need for a bird cage, construction of the tiered seating began more than 3 weeks earlier than expected.”
The AutoCAD drawings were prepared by Laura Barnett from the Layher Design Team.
Thanks to Walton Construction and Paul Houghton of SwiftScaff for the use of this photo.
-
Contact
Paul Houghton
Company
SwiftScaf
Location
-
Components
Details
Scaffolding the new 450 seat theatre at this Melbourne college required a 350m² suspended mat scaffold.
Comments
Not only did the fast installation of Layher Allround enable us to start the project one month ahead of schedule, it also gave us the ability to overlap trades on site to save time
Neil Timms, Walton Construction
MORE SCAFFOLDING PROJECTS

Wallingford Bridge
Wallingford Bridge Strengthening L ocated in Hawkes Bay, the Wallingford Bridge project required smart, efficient scaffolding solutions to support essential strengthening and guardrail installation. Rocket Scaffolding, working with Layher systems, provided the access needed for contractors to safely complete their work under complex conditions. Safe, Practical Solutions for a Time-Sensitive Upgrade Todd Price of Rocket […] Continue reading

Wellington District Court
Wellington District Court Upgrade T he Wellington District Court has undergone a $20 million upgrade to create a more modern, safe environment and improve access to justice services. As part of this project, Geeves Scaffolding (Wellington) was awarded the contract to provide safe access for tradespeople and weather protection throughout the four-stage, 14-month construction process. […] Continue reading