Upright Access Keder Roof
Upright Access used Layher Keder Roof elements, Layher Aluminium Beams and SpeedyScaf to build a full temporary roof for a building that required asbestos materials removed and waterproofing completed.
Weatherproof environment
The job was completed during winter months which proved challenging and took 3 men 8 days with the roof sections craned into place.
As there was asbestos involved shrink wrapping was used and this took over a month to install due to the winter conditions.
Mick Curran said the client was happy with the result and were able to complete their works in a weatherproof environment.
Thanks to Mick Curran of Upright Access for the use of these photos.
-
Contact
Mick Curran
Company
Location
Website
-
Components
Details
3 men 8 days
Comments
Client was happy with the result
Mick Curran
MORE SCAFFOLDING PROJECTS
Offshore Gas Production Platform
DIALOG Fitzroy were engaged by Worley Parsons as the scaffolding contractor for refurbishment of an un… Continue reading
220kV Substation Scaffold
Three sealing-end structures for Auckland’s new 220kV circuits at the point where they return above ground by Cam… Continue reading