Perth Metro Rail Project
Celtic Scaffolding built this birdcage for the Perth Metro Rail Project, Esplanade station. The birdcage enabled Leighton Kumagai Joint Venture to do work on the inside of the roof.
Keeping ahead of the contractors
Celtic Scaffolding needed to span across access voids to the lower platform, which was a tricky job, especially with concrete columns in the way. They erected 17 3.07 bays within the specified type time frame, keeping ahead of the contractors who were following behind. This was Celtic’s first job using Layher scaffolding.
Thanks to Damian Beausang of Celtic Scaffolding for the use of these photos.
-
Contact
Damian Beausang
Company
Celtic Scaffolding
Location
Website
www.celticscaffolding.com.au
-
Components
Details
The birdcage enabled Leighton Kumagai Joint Venture to do work on the inside of the roof
Comments
They erected 17 3.07 bays within the specified type time frame, keeping ahead of the contractors who were following behind
Damian Beausang, Celtic Scaffolding
MORE SCAFFOLDING PROJECTS
Wairau Bridge Cycleway
Scaffold Marlborough were asked to scaffold Wairau River Bridge SH1 in Blenheim. Rob Helstrom of Scaffold Marlborough said Continue reading
Omāroro Water Reservoir
Omāroro Water Reservoir is a bulk water storage facility and key infrastructure project for the Wellington region. WorkZone Scaffolds, along with their partners, Continue reading