Wellington Scaffolding Services were contracted to encapsulate a roof at St. Patrick’s College, Kilbirnie. Kurt Simpson, Group Operations Manager, said “Layher’s Keder Roof XL system was our first choice for spanning the 30 metre by 30 metre building. We knew the encapsulation needed to withstand the harshest of Wellington’s winds and Layher’s Keder Roof XL stood up to the challenging weather conditions.”

“The three-month long project started off with the construction a 10 metre high Layher Allround scaffold around the perimeter of the college building. The Keder Roof XL sections were safely constructed on the ground and then craned into place“ said Kurt.

On Layher’s Design Service Kurt said “we received great service, as always. The Layher Engineering team are always on call for any questions or last minute components we may need.”

Thank you to Kurt Simpson, Group Operations Manager, Wellington Scaffolding Services for the use of these photos.




Wellington Scaffolding Services constructing a Layher Keder Roof XL over St. Patrick's College building
Wellington Scaffolding Services constructing a Layher Keder Roof XL over St. Patrick’s College building

Layher Keder Roof XL provides weather protection for roofing contractors
Layher Keder Roof XL provides weather protection for roofing contractors

Temporary roof safely constructed on the ground and craned into position
Temporary roof safely constructed on the ground and craned into position


MORE SCAFFOLDING PROJECTS


Wellington District Court

Wellington District Court Upgrade T he Wellington District Court has undergone a $20 million upgrade to create a more modern, safe environment and improve access to justice services. As part of this project, Geeves Scaffolding (Wellington) was awarded the contract to provide safe access for tradespeople and weather protection throughout the four-stage, 14-month construction process. […] Continue reading

Peninsula Roof Celebration

Peninsula Roof Celebration Peninsula Roofing and Scaffolding was selected to construct a stage for the Tuia 250 Captain Cook Ngati Hei – Mercury Bay Commemorations in Whitianga. Richard Vetter, Former Director at Peninsula Scaffolding, highlighted how Layher products played a key role in the project’s success: “We used a combination of Layher Allround Scaffolding, Layher […] Continue reading