Scaffolding with More Possibilities. Lighter. Faster. Stronger. Layher.

Car Park Propping

Car Park Propping by Workzone Scaffolds
Car Park Propping by Workzone Scaffolds

Car Park Propping

This Wellington car park sustained damage as a result of the 6.5 earthquake on 21 July 2013. Spalling and cracking to beams supporting the car parks ramps presented real concern considering the risk of aftershocks and the need to remove cars remaining in the building.

15 tonne of Layher Allround

WorkZone Scaffolds, with the support of a local consulting engineer and Layher’s senior design engineer Kenneth Redman, started on site within 5 days of the quake and impressively started removing cars from the lower two levels within 9 days of the quake. In total WorkZone installed more than 15tonne of Layher Allround propping on this project.

Responsive and professional

Graham Burke of WorkZone commented the client was grateful for the responsiveness and professionalism of all parties involved. The client was certainly glad that the propping solution was installed before the second earthquake, (16th of August 2013, measuring 6.6).

Thanks to Graham Burke of Workzone Scaffolds for the use of these photos.



MORE SCAFFOLDING PROJECTS