Westpac Stadium Tattoo
Wellington hosted the Royal Edinburgh Military Tattoo at the Westpac Stadium. The contractor, NZ Festival, engaged Geeves Scaffolding to build the scaffold in order to allow other trades to complete the framework and castle cladding.
Went as planned
“Speed of construction was very important, the erection of the Layher Allround modular system went as planned and was erected as per the designs drawn up by Alex Ignjatovic of Layher” said Tim Geeves of Geeves Scaffolding.
Layher design team
60 tonne of the Layher Allround System was erected in four days using 900 man hours to complete the work. “We found Layher’s design team second to none. They worked closely with us to ensure the build was as fast and as efficient as possible. Thank you to Scott, Alex and the team for their outstanding support on this project” said Tim.
Thanks to Geeves Scaffolding for the use of these photos.
-
Contact
Tim Geeves
Company
Location
Website
-
Components
Details
60 tonne of the Layher Allround erected in four days using 900 man hours
Comments
Speed of construction was very important. Layher’s design team second to none!
Tim Geeves
MORE SCAFFOLDING PROJECTS
Peninsula Roof Celebration
Peninsula Roof Celebration Peninsula Roofing and Scaffolding was selected to construct a stage for the Tuia 250 Captain Cook Ngati Hei – Mercury Bay Commemorations in Whitianga. Richard Vetter, Former Director at Peninsula Scaffolding, highlighted how Layher products played a key role in the project’s success: “We used a combination of Layher Allround Scaffolding, Layher […] Continue reading
Church Road Winery Stage
Church Road Winery in the sunny Hawkes Bay was host to a series of concerts this summer which culminated with Continue reading