SBS Building Invercargill
The revitalising of Invercargill’s SBS Building required an extremely fast turnaround. Brazier Scaffolding Director Glen Brazier said that “The project in the city centre had to be scaffolded, painted and dismantled in a timeframe of just four weeks”.
Limited ground space
The challenge presented to the scaffolders along with the short timeframe was the limited ground space available for the legs.
“Using the Layher Allround System allowed two of the rear elevations to be cantilevered with six to seven lifts all being suspended” he said.
Thanks to Glen Brazier of Brazier Scaffolding for the use of this photo.
-
Contact
Glen Brazier
Company
Location
Website
-
Components
Details
Limited ground space
Comments
Extremely fast turnaround!
Glen Brazier
MORE SCAFFOLDING PROJECTS
Brandon Street Double
Camelspace faced many challenges during this technically complex scaffolding project on Wellington’s Brandon Street. The Continue reading
Whangarei Earthquake Strengthening Roof
Northland Scaffolding were asked to provide exterior scaffolding and a temporary roof structure spanning 26m wide × 45m long Continue reading